If sand bulkage is 25 percent and required dry volume is 2.0 cubic metre, the wet loose volume to be batched is:
Building MaterialsBuilding Materials and ConstructionHARD
Choose the correct answer
A
1.60 cubic metre
B
1.75 cubic metre
C
2.25 cubic metre
D
2.50 cubic metre
Correct Answer
D. 2.50 cubic metre
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Wet loose volume = dry volume x (1 + bulkage) = 2.0 x 1.25 = 2.5 cubic metre.