If 300 cars, 50 buses with PCU 3 and 100 two-wheelers with PCU 0.5 pass per hour, total PCU per hour is:
Transportation EngineeringTransportation EngineeringHARD
Choose the correct answer
A
500
B
650
C
550
D
450
Correct Answer
A. 500
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Total = 300 x 1 + 50 x 3 + 100 x 0.5 = 500 PCU/h.