Civil Engineering MCQJE Level Civil Engineering
For the term heading and benching, the right choice is:
Transportation EngineeringTransportation, Railway, Bridge and TunnelEASY
Choose the correct answer
A
tunnel excavation method in stages
B
road traffic survey
C
pavement compaction only
D
rail welding method
Correct Answer
A. tunnel excavation method in stages
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
tunnel excavation method in stages is the correct association for heading and benching.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.