For reinforcement quantity calculation, which of the following rules or methods is correct?
Estimation and CostingBar Bending ScheduleMEDIUM
Choose the correct answer
A
BBS lists bar shape, diameter, length, number and weight
B
BBS ignores bends and hooks
C
bar diameter is not recorded
D
BBS is a soil classification chart
Correct Answer
A. BBS lists bar shape, diameter, length, number and weight
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
BBS supports steel cutting, bending and billing. Correct option: A.