Civil Engineering MCQJE Level Civil Engineering
For quick exam reasoning in Rate Analysis, identify the correct treatment of deriving item unit rate. Avoid the common trap that wastage never matters.
Estimation and CostingRate AnalysisMEDIUM
Choose the correct answer
A
wastage never matters
B
rate analysis is identical for all items
C
materials, labour, equipment, overheads and profit are considered
D
only contractor name is used
Correct Answer
C. materials, labour, equipment, overheads and profit are considered
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Rate analysis builds realistic unit costs. Correct option: C.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.