Civil Engineering MCQJE Level Civil Engineering
For quick exam reasoning in Bar Bending Schedule, identify the correct treatment of reinforcement quantity calculation. Avoid the common trap that bBS ignores bends and hooks.
Estimation and CostingBar Bending ScheduleMEDIUM
Choose the correct answer
A
BBS lists bar shape, diameter, length, number and weight
B
BBS ignores bends and hooks
C
BBS is a soil classification chart
D
bar diameter is not recorded
Correct Answer
A. BBS lists bar shape, diameter, length, number and weight
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
BBS supports steel cutting, bending and billing. Correct option: A.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.