Civil Engineering MCQJE Level Civil Engineering

For masonry quantity method, which of the following rules or methods is correct?

Estimation and CostingLong Wall Short WallHARD

Choose the correct answer

A

openings are never deducted

B

long walls are measured out-to-out and short walls in-to-in for each layer

C

height is ignored

D

all walls are measured centre-to-centre only

Correct Answer

B. long walls are measured out-to-out and short walls in-to-in for each layer

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

The method accounts for wall junctions layer by layer. Correct option: B.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap