For field interpretation of Approximate Estimate, the issue is early-stage cost planning. What should be selected?
Estimation and CostingApproximate EstimateMEDIUM
Choose the correct answer
A
it ignores building size
B
plinth area or cubic content methods can be used for preliminary cost
C
approximate estimate requires bar bending schedule for every bar
D
it is more exact than final bill
Correct Answer
B. plinth area or cubic content methods can be used for preliminary cost
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Approximate estimates support feasibility and budgeting. Correct option: B.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.