For early-stage cost planning, which of the following rules or methods is correct?

Estimation and CostingApproximate EstimateMEDIUM

Choose the correct answer

A

it ignores building size

B

plinth area or cubic content methods can be used for preliminary cost

C

it is more exact than final bill

D

approximate estimate requires bar bending schedule for every bar

Correct Answer

B. plinth area or cubic content methods can be used for preliminary cost

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Approximate estimates support feasibility and budgeting. Correct option: B.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account