For deriving item unit rate, which of the following rules or methods is correct?
Estimation and CostingRate AnalysisMEDIUM
Choose the correct answer
A
only contractor name is used
B
wastage never matters
C
rate analysis is identical for all items
D
materials, labour, equipment, overheads and profit are considered
Correct Answer
D. materials, labour, equipment, overheads and profit are considered
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Rate analysis builds realistic unit costs. Correct option: D.