For concrete with mineral admixtures or blended cement, curing period should generally be at least:
Concrete Technology & RCCCuringMEDIUM
Choose the correct answer
A
7 days
B
3 days
C
24 hours
D
10 days
Correct Answer
D. 10 days
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Longer curing is required because pozzolanic/blended systems gain strength over a longer period. Reference: Clause 13.5.1 | Page: verify from your official BIS copy/PDF pagination