Civil Engineering MCQCivil Engineering (Shared)

For concrete with mineral admixtures or blended cement, curing period should generally be at least:

Concrete Technology & RCCCuringMEDIUM

Choose the correct answer

A

7 days

B

3 days

C

24 hours

D

10 days

Correct Answer

D. 10 days

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Longer curing is required because pozzolanic/blended systems gain strength over a longer period. Reference: Clause 13.5.1 | Page: verify from your official BIS copy/PDF pagination