For allowance for unforeseen minor items, which of the following rules or methods is correct?
Estimation and CostingContingenciesMEDIUM
Choose the correct answer
A
contingency means contractor profit only
B
it is always negative
C
a percentage provision is included in estimates
D
it replaces detailed quantities
Correct Answer
C. a percentage provision is included in estimates
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Contingencies cover minor unpredictable costs. Correct option: C.