For a doubly-drained clay layer of thickness 2H, the time for 90% consolidation is t₉₀ = T₉₀ × H²/C_v. The time factor T₉₀ is approximately:

Soil MechanicsConsolidation RateMEDIUM

Choose the correct answer

A

0.197

B

0.405

C

0.848

D

1.0

Correct Answer

C. 0.848

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Time factors: T₅₀ = 0.197 (50% consolidation), T₉₀ = 0.848 (90% consolidation), T_100 → ∞. These are standard values from the consolidation equation for double drainage.