Excess lime in brick earth may cause:
Building MaterialsConstruction Materials and PracticeHARD
Choose the correct answer
A
lime blowing
B
zero efflorescence
C
better seasoning
D
higher ductility
Correct Answer
A. lime blowing
Why is this the answer?
Lime nodules expand on hydration and cause cracking or blowing in bricks.
Related Building Materials MCQs
More solved Building Materials questions for AE/JE Civil Engineering exams.
- The 'rebound hammer test' (Schmidt Hammer) gives an indication of:
- 'Alkali-Silica Reaction' (ASR) in concrete causes:
- Which compound in Portland cement is responsible for the early strength gain (3-7 days)...
- The compressive strength of concrete determined from a 15 cm × 15 cm cube, compared...
- A good brick when immersed in a water bath for 24 hours should not absorb more than
- The main constituent of varnish is
Practice more Civil Engineering questions
This MCQ belongs to JE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.