Civil Engineering MCQJE Level Civil Engineering
Engineering estimate: Equilibrium superelevation for speed 80 km/h and radius 200 m is:
Transportation EngineeringTransportation, Railway, Bridge and TunnelHARD
Choose the correct answer
A
0.142
B
0.0018
C
0.252
D
0.011
Correct Answer
A. 0.142
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
For roads, e = V²/(225R) when side friction is zero.