Civil Engineering MCQJE Level Civil Engineering
Choose the most suitable description of running account bill.
Environmental EngineeringEnvironmental Engineering, Estimation, Contracts and EquipmentMEDIUM
Choose the correct answer
A
quality control cube
B
final certificate only
C
tender notice
D
interim payment bill during progress of work
Correct Answer
D. interim payment bill during progress of work
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
interim payment bill during progress of work is the correct association for running account bill.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.