Civil Engineering MCQJE Level Civil Engineering
Bridge-site scenario: For a stair with tread 270 mm and riser 155 mm, the value of 2R + T is:
Building MaterialsBuilding, Materials, Concrete, Drawing and CADMEDIUM
Choose the correct answer
A
425 mm
B
115 mm
C
580 mm
D
695 mm
Correct Answer
C. 580 mm
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Stair comfort relation often checks 2R + T.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.