Analysis of rates includes:
Estimation and CostingHighway Engineering, Estimating, Costing and ContractsHARD
Choose the correct answer
A
only contour interval
B
only contractor name
C
only drawing scale
D
materials, labour, equipment, overhead and profit
Correct Answer
D. materials, labour, equipment, overhead and profit
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Rate analysis builds unit rates from resources and allowances.