Civil Engineering MCQJE Level Civil Engineering
A reviewer rejects three notes on Long Wall Short Wall. Which remaining note is correct for masonry quantity method? Avoid the common trap that openings are never deducted.
Estimation and CostingLong Wall Short WallHARD
Choose the correct answer
A
height is ignored
B
openings are never deducted
C
all walls are measured centre-to-centre only
D
long walls are measured out-to-out and short walls in-to-in for each layer
Correct Answer
D. long walls are measured out-to-out and short walls in-to-in for each layer
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
The method accounts for wall junctions layer by layer. Correct option: D.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.