A reviewer rejects three notes on Approximate Estimate. Which remaining note is correct for early-stage cost planning? Avoid the common trap that approximate estimate requires bar bending schedule for every bar.
Estimation and CostingApproximate EstimateMEDIUM
Choose the correct answer
A
plinth area or cubic content methods can be used for preliminary cost
B
approximate estimate requires bar bending schedule for every bar
C
it is more exact than final bill
D
it ignores building size
Correct Answer
A. plinth area or cubic content methods can be used for preliminary cost
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Approximate estimates support feasibility and budgeting. Correct option: A.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap
Practice more Civil Engineering questions
This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.