A Gantt (bar) chart for project scheduling shows:

Estimation and CostingGantt Chart Bar ChartMEDIUM

Choose the correct answer

A

Resource allocation only

B

Activities as horizontal bars plotted against a time scale, showing planned start, duration, and finish of each activity

C

Only the critical path

D

Material procurement schedule only

Correct Answer

B. Activities as horizontal bars plotted against a time scale, showing planned start, duration, and finish of each activity

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Gantt chart: horizontal bars for each activity along a time scale. Simple to prepare and understand. Limitations: does not show interdependencies between activities; does not identify critical path; difficult to update for large projects. CPM network analysis overcomes these. Progress is shown by shading bars. S-curve shows cumulative cost vs time.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account