A diversion headwork is constructed to:
Irrigation EngineeringHydrology and Irrigation EngineeringEASY
Choose the correct answer
A
Generate tidal power only
B
Raise water level and divert river water into canal
C
Carry road traffic only
D
Store water for many years only
Correct Answer
B. Raise water level and divert river water into canal
Why is this the answer?
Headworks provide ponding and controlled entry into canals.
Related Irrigation Engineering MCQs
More solved Irrigation Engineering questions for AE/JE Civil Engineering exams.
- The 'Lacey''s regime theory' for design of stable alluvial canals gives:
- In irrigation, if the duty D (hectares per cumec) and delta delta (m) over the base...
- A silty soil of high compressibility is represented by
- Freeboard in a dam is the vertical distance between:
- The field irrigation requirement (FIR) for a crop is related to consumptive use (CU),...
- In canals likely to be water-logged, the preferable type of irrigation is
Practice more Civil Engineering questions
This MCQ belongs to SSC JE Civil Paper-I Technical Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.