A diversion head work is constructed to

Irrigation EngineeringIrrigation EngineeringMEDIUM

Choose the correct answer

A

Facilitate the silt entry into the canal

B

Lower water level in the river

C

Regulate the intake of water into the canal

D

Check the erosion of river bed

Correct Answer

C. Regulate the intake of water into the canal

Why is this the answer?

A diversion headwork raises and controls river water for canal off-take