Civil Engineering MCQJE Level Civil Engineering
A completion report is prepared to compare actual cost with:
Estimation and CostingEstimating, Costing and Construction ManagementMEDIUM
Choose the correct answer
A
Rainfall record
B
Bitumen grade
C
Sanctioned estimate
D
Contractor's personal income
Correct Answer
C. Sanctioned estimate
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
Completion report records final expenditure and explains variations.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap