A completion report is prepared to compare actual cost with:

Estimation and CostingEstimating, Costing and Construction ManagementMEDIUM

Choose the correct answer

A

Rainfall record

B

Bitumen grade

C

Sanctioned estimate

D

Contractor's personal income

Correct Answer

C. Sanctioned estimate

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Completion report records final expenditure and explains variations.