Civil Engineering MCQJE Level Civil Engineering
A candidate is comparing options for Measurement Book. Which line correctly handles recording executed quantities? Avoid the common trap that it records only weather.
Estimation and CostingMeasurement BookHARD
Choose the correct answer
A
measurements should be recorded clearly for billing and audit
B
it replaces specifications
C
it records only weather
D
measurement book is optional for all public works
Correct Answer
A. measurements should be recorded clearly for billing and audit
AI Detailed Explanation & IS Code Reference
Unlock the reasoning, formula path and code-linked notes inside your student dashboard.
MB entries support payment and verification. Correct option: A.
ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.
Concept shortcut
IS/IRC reference
Common trap