Civil Engineering MCQJE Level Civil Engineering

A candidate is comparing options for Combined Footing. Which line correctly handles two columns close to each other or near property line? Avoid the common trap that it is never reinforced.

Foundation EngineeringCombined FootingHARD

Choose the correct answer

A

it is used when isolated footings overlap or eccentricity must be controlled

B

it eliminates soil pressure

C

it is used only for water tanks

D

it is never reinforced

Correct Answer

A. it is used when isolated footings overlap or eccentricity must be controlled

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

Combined footings help align resultant load with footing centroid. Correct option: A.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to RRB JE Civil & Allied Engineering CBT-2 Full Mock Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account