A Bill of Quantities (BOQ) in a civil engineering contract is prepared to:

Estimation and CostingBill of QuantitiesMEDIUM

Choose the correct answer

A

Record the contractor name and address

B

Provide a detailed itemized list of all materials, labour, and services required for a project with quantities and rates for tendering purposes

C

Calculate only the labour cost

D

List equipment only

Correct Answer

B. Provide a detailed itemized list of all materials, labour, and services required for a project with quantities and rates for tendering purposes

AI Detailed Explanation & IS Code Reference

Unlock the reasoning, formula path and code-linked notes inside your student dashboard.

BOQ: prepared by engineer/quantity surveyor from drawings and specifications. Contains: item description, quantity (computed from drawings), unit, rate (blank for contractor to fill), amount. Enables competitive tendering on same basis, payment assessment, variation orders, and final accounts. BOQ follows IS 1200 and CPWD/MoRTH specifications.

ScoreCardAI links this solution with subject, topic and difficulty signals so your scorecard can identify weak areas after a full mock test.

Concept shortcut
IS/IRC reference
Common trap

Practice more Civil Engineering questions

This MCQ belongs to AE Level Premium Test Series. Full tests include timed attempts, rank comparison and subject-wise analysis.

Create Free Account